AISHAT A. OWOLABI aishaowolabi@yahoo.com (713-478-8937) EDUCATION: Master of Project Management (MPM) Devry University (Keller Graduate School of
Management, Houston Texas) (2015) Bachelor of Science (Communication Art) Lagos State University, Lagos Nigeria (December
2004) PMI-SP and PMP Certifications – Ongoing SUMMARY OF EXPERIENCE Nine years’ experience in project
planning, control and scheduling. My experience cuts across the oil and
gas, Engineering, and construction industry. Skillful at building
project schedules from start to finish, progress monitoring, reporting,
resource allocation, forecasting, earned value management, critical path
analysis and performance baseline on multiple projects. SYSTEMS PROFICIENCY Primavera P6 (6.0 &7.0 and 8.3), MS Project (2010 and 2013), MS
Word, MS Excel, Power point, Outlook BURROW GLOBAL COMPANIES Houston Texas, Contract (February 2014 To
Date) Project Scheduler Specialist (Kinder Morgan Cow Canyon Expansion
Project, Total Ethylene Processing Unit Project, Total FEL 2 Project) v Built the Level 2
Project Schedule for Kinder Morgan CO2 Cow Canyon plant expansion
project for Cluster 1, 2, 3, and 4 in Cortez, Colorado. v Monitor multiple schedules
(Kinder Morgan Level 3 Baseline Schedule, Kinder Morgan Level 2 Schedule and
the Total Ethylene Processing Unit FEL3 schedule, Total Refrigerator Storage
Construction Project in Primavera P6 and various projects in MS-Project
2013 respectively. v Man-hour loading and
analyzing Estimate to Complete Labor Unit and advising the PM as required v Preparation of various
management reports using Primavera P6. v
Analyze critical path and constraints to determine the effect of
changes to the schedule. v Analyzing variances
in cost and schedule performance against Baseline. v Planned, developed and
setup the Integrated Schedule in Primavera P6 for Engineering Design,
Procurement and Construction (EPC) schedule for the company Project. v Preparing initial CPM and
WBS with manpower requirements, issuing a draft to the project team for
review and compliance, to ensure scheduling requirements are being met
and that it conforms to good CPM scheduling practice to determine
whether it can be improved to more clearly or more accurately represents the
project scope, and Execution
plan
v
Working closely with various disciplines and project teams to ensure
the accuracy and completeness of the schedules. v
Analyze and highlight the overall schedule impact of any variance and
change order. v
Maintained change management system identifying variances from
original scope of work v
Promptly report any schedule slippage to the Planning/Scheduling Lead
and Project Manager so that appropriate actions may be taken to mitigate
delays TURNER AND TOWNSEND Houston
Texas, Contract (March 2013 – December 2013) Project Planning
/Scheduling (Shell Oil Gulf Coast Gas To Liquid Project) v
Creating detail construction schedule for Above Ground (A/G) and
Underground (U/G) Pipelines for the Gulf Coast Gas to Liquid Project (over
$12.5 billion project) at Shell v
Review sub-contractor schedules and consulting with various
disciplines lead on request for update communication to ensure milestones and
project objective is achieved. v Preparation of
various management reports including 30, 60 and 90 day look-head. v Decomposition of Work
Breakdown Structures (WBS) into work packages for better interpretation and
understand by all project leads. v Preparation of
S-Curve showing relationship and manpower distribution between phase 1 &
Phase 2 and across the BDP/define phase. v Participate and
analyzing of project flow diagram using Gantt Chart displays and histograms
in Primavera. v Resource loading of
over 80 million BDP man-hours for the Stick Build/Modularization for both
Phase 1 (Train 1) and Phase 2 (Train 2). v Conducted and
participated in Shell Safety and Project Planners review meetings analyzing
and exchanging ideas on lessons learned from similar projects. v Carried out resource
leveling where necessary to avoid over- allocation of resources v Worked closely with
estimators, risk evaluators, project sponsor and stakeholders by ensuring all
interest are well represented and understand by all parties. v
Updating Level 2 and 3 BDP Schedule using data from the EPCMs v
Support the Project Team in the implementation of an integrated cross
functional EPC master schedule for the Gulf Coast Gas to Liquid project for
Shell. v
Conduct the required project schedule analysis, critical path analysis
and near critical path analysis for Shell Gulf Coast Gas to Liquid Project v
Analyze deviations from the baseline in the Project Master schedule
highlighting bottlenecks/delays and propose corrective actions. SRM GROUP,
Houston Texas (Nov. 2008 – Dec 2012) Project Control/Scheduler ($300Million Jefferson
Refinery, Winnie Texas) v Responsible for
creating WBS, Activity coding and Deliverable Activities, maintaining Logic,
Status update, CPM Analysis, Trending, and Forecasting for Jefferson Refinery
expansion project. v . v Hands on contribution
to the development and maintenance of Work Breakdown Structure (WBS) and that
lead to the establishment of a cost/schedule baseline to move project
forward. v Evaluated durations
against historical or similar projects by liaising with construction managers
and superintendents to determine work durations. v Communicated project
status report to project team and client via weekly meetings. v Identify Critical
Path Activities (CPA) and near critical and advise project team
accordingly. Integrating subcontract schedules with project master
schedule. v Generated monthly progress
status reports, progress curves and reconcile committed costs to actual costs
on a monthly basis. v Developed manpower
histograms to evaluate resource demand levels for all current and
proposed projects. v
Developed, manage, update, and monitor individual project schedules
and integrated overall master program schedule. v Evaluated durations against
historical or similar projects by liaising with construction managers and
superintendents to determine work durations. . CARMAGEN
ENGINEERING New Jersey, (Feb 2006 – Jul 2008) Project
Scheduler (Facility & Pipeline project) v Created Master schedules
and baseline for Valves, pipes and vessel installation projects for the
client. v Maintained the construction
schedule of Mounted Ball Valves, Floating Ball Valves, and full opening check
valves used by oil producing company. Monitored actual progress,
compared to baseline and report progress against schedule in primavera
P6. v Determined and analyzed
critical path activities on Primavera P6 for identification of potential
delay impacts. v Guaranteed the accuracy of
the information that the Project Manager receives and, if necessary,
investigate further by checking with the field engineers if required. v Updated, consolidated,
validated and recorded the Project Baseline Schedule from Primavera P6 with
all the parties actively involved. v Collected and consolidated
the physical progress follow-up for projects and update it in Primavera P6. Nigeria
National Petroleum Corporation (Exploration and Refinery) (Jan 2001-
Dec 2005) Project
Planner/ Scheduler Prepared Work Breakdown Structure (WBS) and
activities on extensive piping for closed loop sample, safety shower &
eye wash upgrade, and recovery oil tank projects at Warri refinery. v Analyzed construction
activities and Identify schedule key milestones dates for engineering,
procurement and construction and all critical Items as specified in the
contract requirement v Established project WBS and
activities with project manager and project engineers on some of our capital
projects such as fire upgrade system, rotating equipment’s such as oil
recovery pump installation etc. v Gather information from the
project team to develop Project Execution Schedule, Project Execution
Plan(CPM), Work Breakdown Structure v Monitoring project expenses
against budget, monitoring weekly on-site activities, monitoring and
prioritizing procurement of material v Creating monthly cost
reports, developed corporate monthly report v Reporting to the
Planning/Scheduling Lead and Manager, responsibility includes prepare the
Project EPC Schedule based upon input from the Project Engineer and his field
staff and the subcontractors v Update the Project
Construction Schedule on a regular basis based upon input from the Project
Engineer and his/her field staff and the subcontractors v Close out the EPC Schedule
at completion of the project to reflect the final actual start and completion
dates of all construction activities. REFERENCE Furnished on request. Owolabi, A.